PMI-SP Tests Schedule Development and Control — Earned Value and Critical Path Under Pressure
The exam tests whether you can build, analyze, and control project schedules — including network diagrams, critical path analysis, and EVM calculations.
Check Your Readiness →Most candidates understand PMI Scheduling Professional concepts — and still fail. This exam tests how you apply knowledge under pressure.
PMI-SP covers schedule management from planning through control. The exam requires performing network diagram calculations, EVM calculations, and making schedule compression decisions. Know the formulas and when to apply each schedule optimization technique.
Add resources to all activities to speed everything up
Only adding resources to critical path activities reduces project duration (crashing); adding resources to non-critical path activities doesn't shorten the schedule. Identify the critical path first, then crash only cost-efficient activities on it.
The project will recover since performance often improves in later phases
SPI of 0.8 means only $0.80 of work has been completed for every dollar planned. Early SPI is the best predictor of final performance. Develop a schedule recovery plan immediately.
Activity B can start 3 days after the project start
SS+3 means Activity B can start 3 days after Activity A starts — not 3 days after the project starts. The lag is calculated from when Activity A begins.
Fast-tracking performs activities in parallel that were planned sequentially — it increases risk but uses existing resources. Crashing adds resources to critical path activities — it increases cost. Candidates apply the wrong technique when cost vs. risk is the stated constraint.
FS: B cannot start until A finishes. SS: B cannot start until A starts. FF: B cannot finish until A finishes. SF: B cannot finish until A starts. SF is rare and often misidentified in exam questions.
Total Float = LS - ES (or LF - EF). Free Float = ES of next activity - EF of current activity. Critical path has zero total float. Candidates confuse these calculations or make arithmetic errors on forward/backward pass questions.
SV = EV - PV. SPI = EV/PV. SPI > 1 means ahead of schedule. SPI < 1 means behind. Candidates who interpret positive/negative variance backwards make wrong schedule health assessments.
The critical path method assumes unlimited resources. In reality, resource constraints create resource-critical paths that may be longer than the unconstrained critical path — candidates who ignore this fail constrained scheduling questions.
PMI-SP tests schedule precision under pressure. Test whether you can calculate and interpret project schedule health correctly.